RS08 PRODUCTION TRANSFER

Headline:

As a follow up to site/location selection service, ROI offers a complete support in production transfer and roll-out until reaching sustainable operations and processes.

Description:

Step 1 – Initial situation
- Meetings with project stakeholders to determine project requirements, timeframe and scenarios
- Creation of basic requirements catalogue
- Introduction of a Site selection dashboard
- Overview of the scope of relocation steps

Step 2 – Preparation and kick-off
- Objective description
- Detailed definition of the study areas of the project
- Project organization and availability of resources approved
- Binding adoption of the deliverables
- Project plan and project guidelines
- Success measurement of the project

Step 3 – Criteria catalogue, profile and specifications
- Development of a plant characteristics with regard to the basic requirements of the plant for the location
- Requirements as input to the site/location selection are defined

Step 4 - Manufacturing concept / relocation planning
- Design of material flows
- Ideal concept preparation
     - Ensuring lean principles

     -
Processes, plant, areas

     -
Employees
- Real concept preparation (taking into account the general conditions of the chosen location)

     -
Equimpent planning, layout planning, media supply

     -
Floor and space planning

     -
Workplace design

     -
Logistics connections

     -
IT planning

     -
Work organization and personnel concept
- Consideration of the requirements from fire protection, environment
- Implementation of planning
- Start of personnel search
- Coordination of all external and internal participants
- Building concept - Option new hall, modification existing hall, definition of required changes

Step 5 – Realization and roll-out:
- Consistent project management, project controlling, management and control of all activities through ROI
- Support in the selection of investments and suppliers (machines, plants, infrastructure, ..)
- Reporting, communication, escalation
- Government authorities management
- Tenders, supplier selection and coordination
- Ramp-up concept
- Personnel search and staffing, development of qualification concepts
- Interim plant management if required

Budget estimate:

From 15 to 150 MDs depending on project scope